Latest updates

Plans are submitted

A planning application for the Lower Otter Restoration Project has been submitted to East Devon District Council.
Click here for details

Working with nature

We’ve put together a handy factsheet on the project.
Click here

Keep up-to-date

Sign-up for project updates

If you’d like to receive emails to let you know about important project updates, please click here.

Contacts

Tell us what you think

To contact the Lower Otter Restoration Project, or to email a member of the project Stakeholder Group, click here.

Updates Contacts

Project factsheet

Q&A

Answers to the most frequently asked questions about the project are available here.

planfaq

Environmental statement

Home Email us
PACCo
Home Your data & privacy Cookies Terms & Conditions Contacts

Website designed and maintained by KOR Communications

© Lower Otter Restoration Project

Lower Otter Restoration Project Search
plans
Call us Updates

Planning application - Timetable

Phase

Estimated dates

Budleigh Salterton Cricket club works commence (part of a separate planning application)

Spring 2021


Stage one vegetation clearance

Jan 2021 – Feb 2021

Stage two vegetation clearance and
Construction phase mobilisation  

May – Jun 2021


Construction phase:

Tidal creek excavations

General earthworks

Highway bridge foundation works

Footbridge foundation works

Big Bank breach works

New South Farm Road highway embankment earthworks formed

Footpath raising works

Jul – Oct 2021


New South Farm Road highway embankment monitored for settlement over nine month period

Footbridge deck installed

Highway bridge deck and features installed

Small culvert structures installed

Service diversions

The estuary sewer pipe diversion works may commence early 2022 (separate to this planning application)

Nov 2021 – Jul 2022

New South Farm Road highway embankment completes; surfacing and features installed

New highway ties into existing road network

Existing Cricket club removal begins

Aug – Oct 2022

Final creeks excavated.

Existing South Farm Road surface removed

Improvements to existing footpath embankments

Nov – Dec 2022


Little Bank breach works

New Budleigh Brook channel connected; existing aqueduct removed

Main Southern breach works

High tide bird islands formed

Landfill area cover finalised

Final landscaping features installed

The FAB-Link project (separate to this planning application) is estimated to start in early 2023. It is not expected to clash with the final works of LORP.

Jan – Feb 2023


Construction phase demobilisation

Mar 2023